Enquire Now
Enquire Now!
I agree to the Terms & Conditions

Brigade Parkside East

Bangalore - Ongoing

RERA STATUS:

PRM/KA/RERA/1251/446/PR/180621/001910 available at https://rera.karnataka.gov.in/

Overview

Introducing CLASSIC & PRIME at Parkside East by Brigade, a unique gated communities where kids can spend quality time with their grandparents, listening to their stories from yesteryears and where grandparents can forget about age and just be kids.

Thoughtfully crafted, keeping in mind the specific needs of varying ages, this community has one set of blocks named CLASSIC, dedicated solely for the seniors, with a range of special services and features. While the other set of blocks named PRIME, caters to the lifestyle choices of today's cosmopolitan families.

These thoughtfully designed 1 & 2 bedroom homes are located strategically on Sarjapur Road in East Bangalore and are blessed with a ready social infrastructure.

Media

Other downloads

Master plans / Floor plans

Masterplan

Download

Floorplans

Download

Application Form

Allotment Form

Download

3D Virtual Tour

Promo Video

Status Gallery

Mar 2020 - North side view: N & P Blocks—Above terrace works in progress; internal wall plastering works in progress; N Block—External wall plastering works in progress
Mar 2020 - North side view: N & P Blocks—Above terrace works in progress; internal wall plastering works in progress; N Block—External wall plastering works in progress
Mar 2020 - North side view: N, P and Q Blocks—Block work in progress; N & P Blocks—Ceiling & internal wall plastering in progress
Mar 2020 - North side view: N, P and Q Blocks—Block work in progress; N & P Blocks—Ceiling & internal wall plastering in progress
Mar 2020 - West side view: L & M Blocks: Block work completed, internal plastering works in progress; M Block—Plumbing works in progress
Mar 2020 - West side view: L & M Blocks: Block work completed, internal plastering works in progress; M Block—Plumbing works in progress
Mar 2020 - South side view: K Block—Blockwork at 4th floor level in progress; Internal wall plastering work in progress
Mar 2020 - South side view: K Block—Blockwork at 4th floor level in progress; Internal wall plastering work in progress
Mar 2020 - South side view: H Block—Ground floor concreting works completed, GF to FF column reinforcement works in progress
Mar 2020 - South side view: H Block—Ground floor concreting works completed, GF to FF column reinforcement works in progress
Mar 2020 - South side view: F Block—GF shuttering and reinforcement works in progress; E Block—3rd floor concreting in progress
Mar 2020 - South side view: F Block—GF shuttering and reinforcement works in progress; E Block—3rd floor concreting in progress
Mar 2020 - North side view: Q Block—4th floor shuttering and reinforcement works in progress; Q Block—1st floor block work in progress
Mar 2020 - North side view: Q Block—4th floor shuttering and reinforcement works in progress; Q Block—1st floor block work in progress
Mar 2020 - West side view: R Block—1st Floor pour-01 slab completed, pour-02 slab shuttering works in progress
Mar 2020 - West side view: R Block—1st Floor pour-01 slab completed, pour-02 slab shuttering works in progress
Mar 2020 - East side view: B & C Blocks—Foundation works in progress
Mar 2020 - East side view: B & C Blocks—Foundation works in progress
Mar 2020 - North side view: A Block—GF shuttering and rebar works completed, concreting works in progress; UG Sump wall shuttering works in progress; B Block—Foundation works in progress
Mar 2020 - North side view: A Block—GF shuttering and rebar works completed, concreting works in progress; UG Sump wall shuttering works in progress; B Block—Foundation works in progress
Mar 2020 - Northside compound wall: Northside compound wall raft reinforcement works in progress
Mar 2020 - Northside compound wall: Northside compound wall raft reinforcement works in progress
Mar 2020 - Front compound wall: Gate erection for Entry and exit completed
Mar 2020 - Front compound wall: Gate erection for Entry and exit completed
1/12

Get In Touch

RERA STATUS:

PRM/KA/RERA/1251/446/PR/180621/001910 available at https://rera.karnataka.gov.in/

PRICE:

1 BHK: 41 Lakh Onwards
2 BHK: 63 Lakh Onwards

TYPE:

1 and 2 bedroom apartments

SUPER BUILT-UP AREA:

65 - 116 Sq.m

CARPET AREA:

39 - 59 Sq.m

Note: (1 Sq.m = 10.764 Sq.ft)

Features

Wading Pool, Swimming Pool, Mini Golf, Jogging Track/Brisk Walk, Outdoor Gym, Senior Friendly Indoor Gym
ADDRESS:

Hadosiddapura Road, Sarjapur Road,
Chikkannahalli, near St. Stephens Marthoma Church,
Bangalore, Karnataka 560 035

Social Infrastructure Nearby

Stanford Speciality Hospital 3.5 Kms
Total Mall 4 Kms
Columbia Asia 4.5 Kms
Sakra World Hospital 5 Kms
Bangalore Central 6 Kms
HSR Layout 8.5 Kms
Narayana Multispeciality Hospital 9 Kms
Koramangala 9.5 Kms

Share

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Click to call Click To Call